Reference/ Residential/ Marsa Penthouse

Marsa
Penthouse

A 640 m² interior fit-out across two floors in Dubai Marina. Joinery, stone and integrated systems were bought and commissioned as one package, so the residence arrived working rather than arriving and then being made to work.

Marsa Penthouse living space at dusk, lit to the evening scene
640m² fit-out
2Floors joined
9Months on site
4Scenes at handover

The brief

The client had bought two apartments on adjacent floors of a completed tower and wanted them to read as one residence rather than two flats with a hole between them. A connecting stair, a single material palette running through both levels, and systems that behave identically in every room.

What it took

Forming a structural opening in an occupied tower: coordination with the building's own structural engineer, out-of-hours craning, and a noise window negotiated with the owners' association before we priced the work. Joinery was made in our own Quoz workshop, stone came from a single block so the veining runs continuously, and lighting, shading and climate were commissioned together on one scene set.


What was installed

01

Joinery

Wall linings, wardrobes, the connecting stair balustrade and all loose-fit furniture, made in our own workshop

Single supplier
02

Stone

Travertine floors and bathroom slabs cut from one block, dry-laid and numbered before fixing

One block
03

MEP alterations

Re-routed services around the new opening, separate metering retained per floor

Coordinated pre-pour
04

Integrated systems

Lighting, shading, climate and audio on one controller, four scenes at handover

One scene set

Four scenes were handed over, not eleven. We came back at ninety days to re-tune them in a furnished, occupied apartment — a practice that came directly out of going back to a house we commissioned in 2021.

“We moved in and everything simply worked. That is rarer than it should be.”

Client, Marsa Penthouse

Credits

01

Contract

Fit-out, single package

02

Scope

Joinery, stone, MEP alterations, lighting, shading, climate, audio, commissioning

03

Completion

2025 — re-tuned at ninety days

All reference projects